Our Experience
Site Country |
Period |
Project Name |
Taiwan |
1999-2001 |
Ho-Ping Coal Fire Power Station
Unit # 1 & 2 |
Thailand |
Feb 2005 |
Ban Rong Po LPG Tank |
Thailand |
2004-2005 |
Songkhla Gas Separation Plant-1
(GPS-1) |
Thailand |
2005-Aug 2006 |
High Temperature Slurry Heater (Australia) |
Vietnam |
Mar2006-Apr2006 |
Kanai LPG Terminal |
Thailand |
Sep 2006-Apr2007 |
Kaeng Koi #2 Power Plant |
Thailand |
Mar 2007-Nov2007 |
Ratchaburi Power Plant (RPCL 2x
700 MW) |
Thailand |
May 2007-Fab 2009 |
Product Quality Improvement Plant # 4 (PQI) |
Thailand |
Jan 2008-Mar 2008 |
Pipe On Call Project |
Thailand |
May 2007-Aug 2007 |
Born Canada Paraxylene Fire Heater |
Thailand |
Nov 2008-Mar 2010 |
PTTUT CUP1&3 |
Thailand |
Aug 2008-Dec 2009 |
PLUTO LNG Project (Fabrication an Export to
Australia) |
Thailand |
Jan 2009-Nov 2009 |
PTT Ethane Separation Plant
(WSPP4) |
Thailand |
Jul 2009-Oct 2010 |
AN AND MMA |
Thailand |
Jan 2009-Sep 2010 |
GLOW PHASE 5(Combined
Cycle/Co-generation Power Plant) |
Thailand |
Oct 2010- Jan2011 |
GLOW PHASE 3 (Pipe Rack Connect From SPP5) |
Thailand |
Jan 2011-May2011 |
IRPC Renew H2 (Pipe Rack) |
Thailand |
Nov 2010-Nov 2011 |
ESSO SRIRACHA CLEAN FUELS (SCFP) |
Thailand |
Nov 2011-Dec 2011 |
IRPC IP PLANT (Vendor List No.
109617) |
Thailand |
Apr 2012-Dec 2012 |
JURONG AROMATICS COMPLEX for SINGAPORE |
Vietnam |
May 2012-Jul 2012 |
LPG REFRIGERATED STORAGE
(VIETNAM) |
Thailand |
Jul 2012-Feb 2013 |
ONSHORE COMPRESSURE STATION 4 (OCS#4) |
Thailand |
Oct 2012-May 2013 |
PNG/LPG (EPC4) for SOUTHEN
HIGHLANDS, PAPUA NEW GUINEA |
Vietnam |
June 2013-Sep 2013 |
HYDROGEN & NYTROGEN STORAGE (VIETNAM) |
Thailand |
Oct 2013-Dec 2013 |
SCG MOC ARU Shut Down (Vendor
List No. 0000191055) |
Vietnam |
Jan 2014-Feb 2014 |
MICCO AN PROJECT 200,000 MTPY (VIETNAM) |
Vietnam |
June 2014-Aug 2014 |
DAP NO.2-VINACHEM PROJECT
(VIETNAM) |
Thailand |
May 2014-Jan 2015 |
CHP II |
Thailand |
Sep 2014-Feb 2015 |
GPSC CUP1 PIPE AND POWER
DISTRIBUTION TO PTT PHENOL II (PPCL#2) |
Thailand |
Nov 2014 |
HP MUD Piping Modification |
Thailand |
Feb 2015 -May 2015 |
LATKRABANG SPP POWER PLANT |
Thailand |
Feb 2015-Jan 2016 |
BANGPOO SPP POWER PLANT |
Thailand |
Nov 2015-Oct 2016 |
CHP II PHASE II |
Thailand |
Dec 2016-Jan 2017 |
GHECO-ONE 660 MW. COAL-FIRED POWER PLANT
(SHUT DOWN) |
Thailand |
Nov 2016-Feb 2017 |
UPGRAGE and REPLACE HHPS 30002&ASSOSIATED
PIPING FOR HTHR (SHUT DOWN) |
Thailand |
Nov 2016-Apr 2017 |
MEAMOH POWER PLANT UNITS 4-7 REPLACEMENT
PROJECT |
Laos |
Nov 2017-Dec 2021 |
HONGSA THERMAL POWER PLANT 3x660
MW. PROJECT |
Thailand |
May 2019-Apr 2022 |
THAI OIL REFINERY (Vender List No. 2004763) |
Thailand |
Jul 2019-Oct 2020 |
MOCD2 PROJECT |
Thailand |
Oct 2019-Mar 2020 |
STAR PETROLEUM REFINERY SPRC (SHUTDOWN
PROJECT) |
Thailand |
Jun 2020 -Jun 2022 |
CLEAN FUEL PROJECT (CFP) |
Thailand |
Nov 2020-Mar 2022 |
CLEAN FUEL PROJECT (CFP) |
Thailand |
Nov 2020-Jun 2022 |
CLEAN FUEL PROJECT (CFP) |